03/12/2019
The EU Procurement thresholds for 2020-2021 have been released.
The new procurement thresholds, which will apply to the public sector from 1st January 2020, have been published. A short summary of the main thresholds is below:
| Type of authority | Type of contract | |||
| Works | Supplies & services | Light Touch Regime Services | Concessions | |
| Central government bodies | £4,733,252 (€5,350,000) | £122,976 (€139,000) | £663,540 (€750,000) | £4,733,252 (€5,350,000) | 
| Sub-central authorities | 
 £4,733,252 (€5,350,000) | 
 £189,330 (€214,000) | 
 £663,540 (€750,000) | 
 £4,733,252 (€5,350,000) | 
For reference:
These changes were published in Delegated Regulations of the Commission:
Public sector- works supplies and services thresholds (EU) 2019/1828
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574807901920&uri=CELEX:32019R1828
Concessions – (EU) 2019/1827
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574807901920&uri=CELEX:32019R1827
and conversion rates from Euro to Sterling are in Commission Communication 2019/C 370/01
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574808223493&uri=CELEX:52019XC1031(01)