Affordable Housing: Funding, Valuation, and Charging Challenges &...
Mar 6 2025
Join us in-person in Birmingham
Read MoreJ Tomlinson Limited v Balfour Beatty Group Limited
The Technology and Construction Court (TCC) has issued a reminder that there are very few scenarios where the courts will overturn a valid adjudicator’s decision.
The dispute referred for adjudication had related to an interim application for payment 30 (IA 30) issued by the claimant (the sub-contractor) which the adjudicator had decided had taken effect as a default payment notice.
The facts were as follows:
BBGL failed to pay and JTL commenced enforcement proceedings.
BBGL raised two challenges to the validity of IA 30 in the enforcement proceedings. These were:
BBGL submitted that IA 30 was not valid because:
The TCC granted summary judgment and enforced the adjudicator’s decision.
The court confirmed the principles that are set out in Hutton Construction Limited v Wilson Properties (London) Limited[1]. In the case the court confirmed that it adjudicators’ decisions will be enforced unless the adjudicator has exceeded his jurisdiction to decide the dispute or there has been a breach of the rules of natural justice.
The only exceptions are where:
BBGL did refer to either of the Hutton exceptions or try to explain why these should apply to the present case. BBGL’s arguments that were based on contractual interpretation did not provide a defence to enforcement of the adjudicator’s decision.
Paying parties should be careful to respond to payment applications and ensure that all necessary payment or pay less notices are given on time, otherwise sums may become due for payment by default. This is especially important in the current climate, where due to COVID-19 lockdown restrictions more and more parties and their professional teams are working remotely and compliance with strict procedural requirements (e.g.) for service of physical copies of payment applications may not be possible.
This case is a reminder that failure to follow strict contractual requirements regarding service of notices will not necessarily render payment applications invalid. Paying parties therefore need to ensure they respond promptly to payment applications, even where the application may not have been made in strict accordance with relevant contractual terms.
The TCC has reinforced its policy of supporting that temporary finality of adjudicator’s decision (by which it is meant that a paying party must “pay now and argue later”). As the Judge explained “…the paying party, dissatisfied with an adjudicator’s decision, may embark upon a substantive resolution of the dispute…but is expected to comply with the adjudicator’s decision in the meanwhile…”
Written by Matthew Phipps and Hannah Plummer
[1] [2017] EWHC 517 (TCC), [2018] 1 All E.R. (Comm) 524, [2017] 3 WLUK 419
We use necessary cookies to make our site work. We'd also like to set optional analytics cookies to help us improve it. We won't set optional cookies unless you enable them. Using this tool will set a cookie on your device to remember your preferences. For more detailed information about the cookies we use, see our Cookies page.
Necessary cookies enable core functionality such as security, network management, and accessibility. You may disable these by changing your browser settings, but this may affect how the website functions.
We'd like to set Google Analytics cookies to help us to improve our website by collection and reporting information on how you use it. The cookies collect information in a way that does not directly identify anyone.
For more information on how these cookies work, please see our Cookies page.